(Gazprom) Water treatment / 2013
The Astrakhan Gas Processing Plant
Phase I & II of the gas facility retrofit project included an expansion of Production Facilities No.3 and No.6.
Process
- Counter-current Ion Exchange with an Additional Bed (Water Softening)
- Demineralization
Capacity
- Demineralized Water: 500 m3/h br>
- Treated Steam Condensate: 300 m3/h
Equipment
- Sorption Filters
- SAC Filter (in the H+ Form)
- SAC Filter (in the Na+ Form)
- Counter-current SAC (in the Na+ Form) with an Additional Bed
- Two-Stage Osmosis Unit
- Steam Condensate Purifier
(Novatek) water treatment / 2015
Yamal LNG
Phase I & II of the gas facility retrofit project included an expansion of Production Facilities No.3 and No.6.
Process
- Dyclar Dynamic Clarification & Seawater Application
Capacity
- 250 m³/h
Equipment
- Dyclar Dynamic Clarifying Filter
Services