The Astrakhan Gas Processing Plant

Phase I & II of the gas facility retrofit project included an expansion of Production Facilities No.3 and No.6.

Process
  • Counter-current Ion Exchange with an Additional Bed (Water Softening) 
  • Demineralization
Capacity
  • Demineralized Water: 500 m3/h br>
  • Treated Steam Condensate: 300 m3/h
Equipment
  • Sorption Filters 
  • SAC Filter (in the H+ Form)
  • SAC Filter (in the Na+ Form)
  • Counter-current SAC (in the Na+ Form) with an Additional Bed 
  • Two-Stage Osmosis Unit 
  • Steam Condensate Purifier 


(Novatek)​ water treatment / 2015

Yamal LNG

Phase I & II of the gas facility retrofit project included an expansion of Production Facilities No.3 and No.6.

Process
  • Dyclar Dynamic Clarification & Seawater Application
Capacity
  • 250 m³/h
Equipment
  • Dyclar Dynamic Clarifying Filter
Services
  • Equipment Supply

Yamal LNG